PCL Constructors Westcoast Inc. announced it successfully installed the skybridge connecting the Clinical Support and Research Centre (CSRC), opening in 2029, to the new St. Paul’s Hospital.
The two-storey skybridge creates a vital connection between the future hospital and the CSRC, a new 12-storey, 34,400 square-metre facility that will accommodate research and corporate services staff, medical offices, a childcare centre and below-grade parking.
Through close coordination among Providence Health Care, Diamond Schmitt Architects, Glotman Simpson, Solid Rock Steel and PCL’s project teams, the skybridge was installed in September 2026, four months ahead of its originally planned January 2027 installation date. Advancing the schedule provides additional time for integration and commissioning activities ahead of the new St. Paul’s Hospital’s targeted opening in February 2027 while minimizing future impacts to the main road between the facilities.