CSRC Skybridge
Solid Rock Steel fabricated and erected the two-storey skybridge connecting the new Clinical Support & Research Centre (CSRC) to the new St. Paul's Hospital. The bridge is 26 m (85 ft) long and 3.5 m (11.5 ft) wide and weighs approximately 136,000 kg (300,000 lb).
To reduce work at height above an active roadway and hospital entrance, our team spent months assembling the bridge at ground level. It was built on custom stands engineered to match its final slope and loading conditions, which kept stresses low during erection. Once the bridge was lifted into place, our crews welded it into its final position on site.